Warehouse Unit Demolition in Swiftfields, Welwyn Garden City

In August we was successfully awarded a 9 week contract for our major client in Welwyn Garden City, Herts. 

The works consisted of total demolition to part of a large warehouse unit down to the ground slab level and a full soft strip out, Mezzanine floor removal in another part of the building. 

The total demolition works were carried out by two of our Volvo excavators with various attachments.  While the soft strip out works were carried out by a gang of 10 operatives and one of our 1.5 mini diggers with a rotation grab with all the rubbish arisings being carried away out into our 40 yard bins. 

We successfully complete these works in 8 weeks cutting one week of the programme with no reported incidents.  

Swiftfields Demolition WGC Swiftfields Demolition WGC Swiftfields Demolition WGC