Occupied office block strip-out, Euston, London

Reliance have recently completed a 4 week contract for one of our regular client in an occupied office block in Euston, London.

The works required a gang of 8 demolition and labourer operatives working 6 days a week to carry out the works, the works consisted of a full soft strip of the 3 floor removing ceilings, walls, raised floors and M & E services, soft strip out of toilets and stud work removal of mansard roofs.

All rubbish arising were cleared away via a lift in 3 different times periods, 6-8am, 12-2pm and 4-6pm, with the materials being loaded into 3 different bins ready to be recycled, wood, scrap metal and general rubbish. All works were completed on time with no reported incidents with the site ready to be handed back to the client.