Euston Road Camden Town – Strip out

In October Reliance Demolition was awarded a six week contract for a new client in Camden Town, London, as the building was occupied this job was a bit tricky as the client wanted three floors stripped at the same time and the whole contract had to be completed in time for Christmas.

The works required 3 gangs of 6 operatives working 6 days a week, the three floors were stripped out completely removing floor coverings, stud walls, ceilings and M & E services and also the floor screed in certain areas had to be removed at weekends and cleared away.

A scaffold gantry and hoist were erected at the back of the building to allow us to remove the materials from each floor.

All the rubbish arisings were segregated and stock piled on the gantry ready to be loaded away into our 40 yard bins and sent to the appropriate recycling plants.

The works were completed on time with minimum disruption and noise to the remaining tenants in the building.