Bow Lane, London

In November Reliance Demolition were instructed to carry out full soft strip out works to two big shops in Bow Lane, London for a new client.

This job was a challenging one as Bow Lane is a very tight street in London and the works required out of hours loading between 6am and 8am, all the rubbish arisings had to be cleared every morning on two of our transit tippers.

The works comprised of 3 floors, basement, ground and 1st floor being totally soft stripped of stud and brick walls, floor coverings, ceilings and M & E and terrazzo tiles and screed on the ground floor, breaking up of the screed could only be done between the hours of 6am-8am due to other shops in close proximity and as to not cause to much disruption to the local neighbours, we had a time period of 7 weeks to complete these works before the Christmas shut down and as per usual we finished the works on time and handed the site back to the client for inspection.